Case Study

Chartwood School

Design and Build – Full-Building MEP Refurbishment from Core.

PROJECT WORK

Full delivery from Stage 2 to Stage 4 design, construction – commissioning and full surveying practices to ensure the project stayed in budget.

LOCATION

REDHILL

PROJECT VALUE

£1.6M

£1.6M

PROJECT VALUE

40 Weeks

PROJECT DURATION

Project Details

With the school having been completely destroyed in a fire, the building was stripped out to the core envelope.  The school was fully refurbished with all new MEP services, Plant Rooms, BCWS Supplies, LTHW, DX Air Conditioning, Ventilation, AHU & Kitchen Extracts,  Gas Services, Power, Internal / External Lighting, Emergency Lighting, Fire Alarms, CCTV, Data, Access Control, Security, Building Management Systems.

VME was responsible for the full delivery from Stage 2 to Stage 4 design, construction/commissioning and full surveying practices to ensure the project stayed in budget.