PROJECT WORK :
There was great feeling on site Friday as VME kick off July with the refurbishment of three ‘local’ leisure centres! Totton, Applemore and Ringwood. Full validation, design and build package tailored to meet the clients concept specifications. VRF AC, comfort cooling, MVHR ventilation, WC / washrooms, power, lighting, FIre Alarm & BMS upgrades.
Nice touch to be tasked with a 33% carbon reduction, achieved with H/T air source mixing traditional LTHW / DHW heat Plates, BMS and HE HVAC.
All to be installed by our in house trades, it’s fair to say who are absolutely delighted to be working locally, most of us have taken to the pool or had a humbling on these courts over the years!
To the teams still working across the country and afar, your turn next..
Loving the job!
James Child
VME Managing Director
LOCATION:
RINGWOOD, TOTTON & APPLEMORE lEISURE CENTRES
PROJECT STARTED ON :
January 2020
PROJECT WORK :
There was great feeling on site Friday as VME kick off July with the refurbishment of three ‘local’ leisure centres! Totton, Applemore and Ringwood. Full validation, design and build package tailored to meet the clients concept specifications. VRF AC, comfort cooling, MVHR ventilation, WC / washrooms, power, lighting, FIre Alarm & BMS upgrades.
Nice touch to be tasked with a 33% carbon reduction, achieved with H/T air source mixing traditional LTHW / DHW heat Plates, BMS and HE HVAC.
All to be installed by our in house trades, it’s fair to say who are absolutely delighted to be working locally, most of us have taken to the pool or had a humbling on these courts over the years!
To the teams still working across the country and afar, your turn next..
Loving the job!
James Child
VME Managing Director
We have worked hard to achieve the following accreditations for the Company and the relevant person within our Team, which Demonstrate our desire to be fully conversant & compliant to deliver your project.